CLIENT
SIOM PARAGUAY
The new SIOM Group plant in Paraguay stands out for its cutting-edge technology, designed to produce 1,200 tons per year of high-chromium and carbide steels — key components used for mill linings in the mining industry.
This growth and vertical integration project allows SIOM to generate its own raw materials and recycle products that have reached the end of their lifecycle, turning them into new supplies for mining projects.
START DATE
2023
EXECUTION TIME
8 months
LOCATION
Villeta
BUILT AREA
743 m2